The agreement for the master plan composing has been signed

This project is made possible through a 760,000-euro grant, KfW bank investment and will include:

  1. Analyze and evaluate the current state of the transmission network and the mode of operation.
  2. Forecasts of cargo, generation and transit for a period of 15 years.
  3. Building a network development strategy and forecasting possible funding for its optimization.
  4. Assistance in the methodology for setting the transmission tariff.

OST emphasizes that these are the real steps being taken to renew and optimize the transmission network.

This project will pave the way for a number of other projects and investments to strengthen the transmission system, increase supply security and enable the integration of new generators in our country.