Projects implemented

Construction of the 400 kV line between Albania and Kosova
May 9, 2014
Projects in implementation
March 23, 2018

Completed Projects

CONSTRUCTION OF THE 400 KV INTERKONECTOR LINE TIRANA 2 – KOSOVO B

Project financing is done by the German Government through KfW Bank.

The 400 kV line will have a length of 242 km (162.5 km new line and 80.5 km complement of second district in the first part of the completed line Tirana in Podgorica), 155.5 km in the territory of Albania. The project has entered the phase of the impoundment and is expected to be fully operational by 2016.

 

 

 

 

 

CONSTRUCTION OF THE NEW DISPECER NATIONAL CENTER

THE NEW SCADA / EMS CONTROL SYSTEM OF THE NATIONAL CENTER DISPECTS IS ONE OF THE MOST IMPORTANT PROJECTS OF THE TRANSMISSION SYSTEM OPERATOR.
The central unit of the new SCADA / EMS system and facilities for its use are temporarily concentrated in the control room of N / st 400 kV Tirana2. This project is very complex and includes:

– Telecommunication system including the extension of about 450 km Optical Fiber (OPGW) and other telecommunication equipment such as RTU, PLC, MUX, PABX, providing data acquisition for SCADA and EMS systems from N / Transmission System Stations , KESH plants and N / main stations of CEZ Shpërndarje.

– SCADA System with Data Collection, Event Processing, Calculation of Data, Parameter Limit Monitor, Reporting, Remote Command, etc.
– Energy Management System (EMS) with Load Prediction Functions, Hydraulic Reserve Management, Generator Engagement, Transaction Evaluation, Status Assessment, Power Flow Calculation, Insecurity Analysis, etc.
– Automatic control of the Generators (AGC) of the Drum Cascade, for frequency control and the maintenance of the exchange balance with the neighbors.
– New building of dispatcher center and OST

The SCADA / EMS system enables real-time monitoring and monitoring by the national dispatcher center of the power system, optimally operating from a technical and economical point of view, increasing reliability of operation and quality of power supply.
It optimizes the joint exploitation of the water reservoir of the Drin cascade, other sources of power generation and exchanges with neighbors.
The SCADA / EMS system is a necessary tool for operating in the regional electricity market, for which the Albanian government has received relevant engagements with EU institutions.
The system enables the receipt and delivery of real-time data with the neighboring systems with which the TSO has interconnection links.
The operation of this project is a necessary condition for the operation of our electric power system in parallel synchronous with the European transmission network in compliance with all the technical criteria, and is the latest technical condition for the allocation of the TSO in the European Network of Operators of the System Transmission for Electricity (ENTSO-E)
The project is in the phase of testing, while the new building of the dispatch center and the OST has remained unfinished due to the bankruptcy of contractor Falcione Italy. From numerous meetings with ABB Italia, ABB & Falcione consortium leader, it was agreed that the building will be completed under ABB’s responsibility as the lead company of this consortium. The completion time of the building is projected to be the beginning of 2015.

 

New building of dispatcher center and OST

The SCADA / EMS system enables real-time monitoring and monitoring by the national dispatcher center of the power system, optimally operating from a technical and economical point of view, increasing reliability of operation and quality of power supply.
It optimizes the joint exploitation of the water reservoir of the Drin cascade, other sources of power generation and exchanges with neighbors.
The SCADA / EMS system is a necessary tool for operating the regional electricity market, for which the Albanian government has received relevant engagements with EU institutions.
The system enables the receipt and delivery of real-time data with the neighboring systems with which the TSO has interconnection links.
The operation of this project is a necessary condition for the operation of our electric power system in parallel with the European transmission network in accordance with all the technical criteria and is the latest technical condition for the allocation of the TSO in the European Network of Operators of the Transmission System for Electricity (ENTSO-E)
The project is in the phase of testing, while the new building of the dispatch center and the OST has remained unfinished due to the bankruptcy of contractor Falcione Italy. From numerous meetings with ABB Italia, ABB & Falcione consortium leader, it was agreed that the building will be completed under ABB’s responsibility as the lead company of this consortium. The completion time of the building is projected to be the beginning of 2015.

The project is in the implementation phase and is expected to be fully operational by the end of 2015.
As you can see, the project has a very broad reach including the western and eastern parts of the south of Albania.
The construction of the 110 kV line Babice – Saranda closes in the ring an important part of the 110 kV electrical network, meeting the N-1 static safety criteria. The line crossing in the Ionian coastline creates the possibility of N / st 110/20 kV construction in this area, to improve the electrical infrastructure as a necessity for the development of tourism.
Strengthening of N / st 400/110 kV Zemblak and extension of the 110 kV network in the southeastern area will also close to the ring a part of the existing 110 kV network. Under these conditions, the possibility of supplying the Southern area, through the power flow introduced by N / st 400/110 kV of Zemblak, is created. Consequently, the power flux coming from 220 kV network lines will be reduced by better balancing the South Korean 220 kV ring, which is a problem for the security of supply of a large area.
The 110 kV line in the Vjosa Valley will create the possibility of connecting to the transmission network of a part of the plants that will be built in the flow of this river.

The project as a whole is justified by the elimination of unused energy and the great benefit that it brings to the reduction of electricity losses.