Projects in implementation

Projects implemented
March 23, 2018
Provisional Rules for the Balancing Mechanisml OST sha
June 21, 2018

Projects at the implementation stage

Projects OST sh.a. 2016 – 2017

1. Project: “Construction of 400 kV line Albania – Kosovo”,

Contract date is: 12.12.2013

Date of entry into force of the contract: 16.04.2014

Date of Completion: 16.06.2016.

 

2. Project: “Construction of two new N / 110/35/20 kV Orikum and Himara stations”:

Contract Date: 17.11.2016

Date of entry into force of the contract: 30.12.2016

Deadline: 27.02.2018

 

3. Project: “400 kV Extension of N / Koman HPP Station”

Contract Date Date: 03.05.2017

Date of entry into force of the contract: 31.05.2017

Deadline: 31.05.2018.